Please see below for a up to date time line of planned closures on the A1/A14:

  • Full Closure Planned A1 NB Buckden to Brampton Hut Exit Starting 13th July to 15th July for 2 Nights (21:00 to 06:00) Friday 13th July & Saturday 14th July (contingency) Friday 13th July closure hours will be 21:00 to 07:00
  • Full Closure Planned A1 SB Alconbury to Brampton Exit starting 13th July to 15th July for 2 Nights (21:00 to 06:00) Friday 13th July & Saturday 14th July (contingency) Friday 13th July closure hours will be 21:00 to 07:00
  • Full Closure Planned A1 SB Alconbury to Buckden starting 16th July to 21st July for 2 Nights (21:00 to 06:00)
  • Full Closure Planned Brampton Road Including A1 SB Brampton Exit slip starting 14th July to 15th July for 2 Days (08:00 to 17:00)
  • Full Closure Planned Brampton Road Including A1 SB Brampton Exit slip starting 19th July for 1 Night (21:00 to 06:00)
  • Full Closure Planned A14 EB Jct 20 to Jct 21 starting 16th July to 21st July for 2 Nights (21:00 to 06:00)
  • Full Closure Planned A14 EB Jct 27 to Jct 29 starting 14th July for 1 Night (22:00 to 06:00)
  • Full Closure Planned A14 WB Jct 28 to Jct 27 starting 14th July for 1 Night (22:00 to 06:00)
  • Full Closure Planned Hattons Road (B1050) starting 15th July to 20th July for 5 Nights (21:00 to 06:00)
  • Full Closure Planned A428 EB to A14 EB Jct33 Exit Slip starting 11th July to 14th July for 3 Nights (21:00 to 06:00)
  • Full Closure Planned A428 EB to A14 EB Jct33 Exit Slip starting 16th July to 21st July for 3 Nights (21:00 to 06:00)
  • Full Closure Planned A14 WB Jct36 to Jct31a starting 11th July to 14th July for 3 Nights (21:00 to 06:00)
  • Full Closure Planned A14 WB Jct36 to Jct31a starting 16th July to 21st July for 3 Nights (21:00 to 06:00)
  • Full Closure Planned A14 EB Jct 27 to Jct 29 starting 21st July to 23rd July  for 2 Nights (22:00 to 06:00)
  • Full Closure Planned A14 WB Jct 28 to Jct 27 starting 21st July to 23rd July  for 2 Nights (22:00 to 06:00)
  • Full Closure Planned A14 WB Jct 29 Entry Slip starting 17th July to 20th July  for 2 Nights (22:00 to 06:00)

Please click here to download A14 C2H Improvement Scheme, day time & night time Lane and Slip Road Closures, and click here for a schedule of A14 Huntington to Cambridge improvement scheme.